Estimate to Complete (ETC)

The expected cost needed to complete all the remaining work for a schedule activity, a work breakdown structure component, or the project.

-- PMBOK

See : Earned Value Management (EVM)


Formulas

  1. ETC based on new estimate

  2. EAC using atypical variances
    ETC = BAC - EV

  3. ETC using typical variances
    EAC = ( BAC - EV ) / CPI


See also