Actual Cost(AC)
Total costs actually incurred and recorded in accomplishing work performed for a schedule activity or work breakdown structure(WBS) component. Actual cost can sometimes be direct labor hours alone, direct costs alone, or all costs including indirect costs. Also Referred to as the actual cost of work performed(ACWP). -- PMBOK

See : Earned Value Management (EVM)